How long does an extension take?

How long does an extension take?

Every project is different, but here are the typical build times we see on site, and what makes a job quicker or slower.

Typical build times on site

  • A small single-storey extension: usually around 8 weeks
  • A loft conversion: usually 5 to 7 weeks
  • A two-storey extension: usually 12 to 16 weeks
  • A new build or self build: usually 12 to 16 weeks

These are build times once we are on site. Every project is different, and we give you a programme for your own job before work starts.

Before we start on site

Design, planning permission where it is needed, and the building warrant all come before the build. How long that takes depends on the project and on the council, so it is worth starting the design stage well before you want the builders in.

Our sister company, CWJ Architectural Design Services, handles the drawings, planning and the building warrant, so the build can be planned while the paperwork is in progress.

What affects the build time

  • The size and complexity of the project
  • What is found in the ground or behind existing walls once work starts
  • Weather, especially during groundworks and before the roof is on
  • Lead times on windows, doors, steels and kitchens
  • Changes to the design once the build is under way

How we keep it on track

Our own team builds it and runs the programme, so there are no separate trades for you to coordinate. Long lead items are ordered early, and you hear from us before you have to ask, including when something changes.

Single storey rear extension on a Scottish sandstone house, with sliding glass doors open to a new kitchen (illustrative image)
Talk it through

Every project starts with a site visit

Guides only go so far. We come out, look at the house and talk through what is involved for yours.

Design, planning, the building warrant, the price and the build are all handled by one company, so you have one team to ask.

See house extensions →

Questions

Common questions

How long does a single-storey extension take?

A small single-storey extension usually takes around 8 weeks on site. Every project is different, and you get a programme for your own job before we start.

How long does a loft conversion take?

Usually 5 to 7 weeks on site, depending on the size and layout of the loft.

How long does a two-storey extension or new build take?

Usually 12 to 16 weeks on site for a two-storey extension, new build or self build.

Does the time include planning and the building warrant?

No. These are build times on site. Design, planning and the building warrant come first, and the time they take depends on the project and the council.