Dormer Loft Conversion, Kilmarnock
In progress

Dormer Loft Conversion, Kilmarnock

A full width rear dormer on a traditional Kilmarnock home, built entirely under a full temporary tin lid roof so the house stayed dry and the work never stopped for the weather. Cedral cladding, a Sikalastic RoofPro flat roof, slates matched to the existing roof, new steelwork and a reworked upstairs with a new bathroom. Now on the home straight.

Dormer loft conversion · Kilmarnock

About this project

This traditional slate roofed house in Kilmarnock had rooms in the roof with sloping ceilings and little standing height. The answer was a full width dormer across the back of the house, giving far more usable space upstairs without the upheaval of moving.

The dormer lifts the rear of the roof to give full headroom, more floor space and far more daylight. Upstairs has been reworked around it, with new partitions for the bedrooms, changes to the hallway and a new bathroom with a shower.

The work started in late August 2026. Before a single slate came off, we put a full temporary roof, the tin lid, over the whole house. It is a scaffold roof with its own sheeted cover, so the old roof could be opened right up while the house below stayed dry, and the team could keep working through wind and rain without losing days. On a loft conversion in the west of Scotland it makes all the difference. With the house covered, the rear slope was stripped, the existing roof supported, and new steelwork put in to carry the dormer to the structural engineer's design.

The dormer itself is timber framed, sheathed, wrapped and insulated, then finished in Cedral cladding, our go to low maintenance cladding for dormers. The flat dormer roof is a Sikalastic RoofPro liquid applied system, and where the dormer meets the main roof, lead flashings were dressed in and the slates made good to match the existing roof. New powder coated aluminium windows complete the outside. The steel has fire protection and the new partitions are built to the fire and sound requirements of the building warrant.

As of late October 2026 the dormer is complete and clad in Cedral, the windows are in, the tin lid has come off, the rooms are boarded and the shower floor is prepared. Next comes plastering, tiling, joinery and decoration. You can follow it on our YouTube channel as the Kilmarnock loft conversion, and we will keep adding to this page until handover.

Project facts

  • Location
    Kilmarnock, East Ayrshire
  • Project
    Rear dormer loft conversion and upstairs alterations
  • Status
    In progress, outside complete and finishes under way (October 2026)
  • Features
    Full temporary tin lid roof over the house, structural steel, timber framed dormer with Cedral cladding, Sikalastic RoofPro flat roof, slates made good to match the existing roof, aluminium windows, new partitions and bathroom

Scope of work

  • Scaffold and a full temporary roof over the house
  • Strip and open up the rear roof slope
  • Temporary support and new structural steelwork
  • Timber framed dormer, decking, membranes and insulation
  • Sikalastic RoofPro liquid applied flat roof on the dormer
  • Cedral cladding to the dormer
  • Lead flashings and slates made good to match the existing roof
  • Powder coated aluminium windows
  • New partitions and changes to the upstairs layout
  • Bathroom with new shower floor, waste and ventilation
  • Electrics, plasterboard, plastering, joinery and decoration (to come)
  • Full project management by our own team
Stage by stage

How this loft conversion is coming together

From the scaffold going up in August 2026 to the tin lid coming off in late October. This job is still in progress, and we add each new stage as it happens.

  1. August 2026
    August 2026

    Scaffold up

    Scaffold went up front and back to give safe access to the roof, with protection laid over the driveway and the boards up at the front.

  2. Early September 2026
    Early September 2026

    New layout upstairs

    Inside, the old stud walls upstairs came out and new partitions were framed to the new bedroom layout.

  3. September 2026
    September 2026

    The tin lid goes on

    Before any slates came off, a full temporary roof went up over the whole house. With the tin lid on, the roof could be opened right up while the house stayed dry, and the team could keep working whatever the Scottish weather did.

  4. September 2026
    September 2026

    Opening up the roof

    With the house covered, the rear roof slope was stripped and opened up. The existing roof was supported while the new steel went in to carry the dormer.

  5. Mid September 2026
    Mid September 2026

    Framing the dormer

    The new dormer was framed in treated timber, with the window openings, roof joists and cheeks all built to the engineer's design.

  6. Mid September 2026
    Mid September 2026

    Dormer takes shape

    Seen from the scaffold, the dormer now ran across the rear of the house, giving full standing headroom in the rooms below.

  7. Late September 2026
    Late September 2026

    Decked and insulated

    The roof was decked, the walls sheathed and wrapped, and insulation fitted through the walls and ceilings.

  8. Late September 2026
    Late September 2026

    Inside the dormer

    Inside, the new rooms could be seen properly for the first time, with full height walls and big window openings to the back.

  9. Early October 2026
    Early October 2026

    Dormer complete

    The dormer roof was finished with Sikalastic RoofPro, a liquid applied roofing system, lead flashings were dressed in and the slates were made good to match the existing roof.

  10. October 2026
    October 2026

    Boarding out

    With the dormer weathertight, plasterboard went up on the walls and ceilings of the new rooms.

  11. October 2026
    October 2026

    Shower floor

    In the bathroom, the floor was opened up to run the new shower waste, then boarded and prepared for the tray and tanking.

  12. October 2026
    October 2026

    Windows in

    The new powder coated aluminium windows went into the dormer, bringing far more daylight into the rooms upstairs.

  13. October 2026
    October 2026

    Cedral cladding

    The dormer was clad in black vertical Cedral boards, with matching trims, a new gutter along the dormer roof edge and the aluminium windows set neatly into the cladding.

  14. Late October 2026
    Late October 2026

    Linings and finishes

    The last of the insulation and linings went in around the eaves and coombs, ready for plastering, joinery and decoration.

  15. Late October 2026
    Late October 2026 · Latest

    The tin lid comes off

    With the outside finished, the tin lid came down and the new dormer could be seen properly: black Cedral cladding, aluminium windows and slates matched to the existing roof. Inside, plastering, the bathroom and the finishes are next.

On camera

Watch the build

Short updates filmed on site as the job has gone along.

Gallery

Project photos