What could your extension cost? Get a guide price in 60 seconds → Call 0345 956 9811  |  WhatsApp
Two Storey Self Build, West Kilbride
In progress

Two Storey Self Build, West Kilbride

A two storey self build joined onto a traditional stone cottage in open countryside above West Kilbride, adding two bedrooms, a bathroom and a full master suite with a covered balcony. On site now and nearly over the line.

Two storey self build · West Kilbride

About this project

This detached stone cottage sits in open countryside above West Kilbride. The plan was a substantial two storey self build that sits alongside the original building and connects straight into it, giving the house far more space.

Downstairs, the new build adds two new bedrooms, a bathroom and a hallway with a new staircase. Upstairs is a full master suite: bedroom, dressing area, en-suite and a snug, opening out onto a covered balcony. The existing cottage is being altered around the entrance, utility, kitchen and hallway so the old and new work as one house.

The build started in May 2026. We cleared the site, lowered the access road to meet the building regulations, then dug and poured the foundations, built the substructure and laid the slab. A short pause while the updated structural drawings came through for the steel was used to get ahead with the groundworks and drainage. The timber frame went up over the summer, followed by the first floor, the roof, windows, doors and solar panels.

Joining a new two storey building onto an old stone cottage takes care. The cottage had to stay structurally secure and weathertight at every stage, and the opening through into the existing house was made once the new building was closed in.

As of October 2026 the outside is nearly complete, the scaffold is down, the plasterboard is on and first fix is almost done. Next comes plastering, second fix and the finishes. You can follow it on our YouTube channel too, as the West Kilbride self build, and we will keep adding to this page until handover.

Project facts

  • Location
    Near West Kilbride, North Ayrshire
  • Project
    Two storey self build joined onto a detached stone cottage
  • Status
    In progress, first fix nearly complete (October 2026)
  • Features
    Timber frame, two new bedrooms and bathroom, staircase, master suite with dressing area, en-suite and snug, covered balcony, solar panels

Scope of work

  • Site set up, clearance and a lowered access road
  • Foundations, substructure, drainage and soakaway
  • Insulated ground floor slab
  • Timber frame kit, first floor and staircase opening
  • Roof, insulation and solar panels
  • Windows, external doors and covered balcony
  • Opening through and alterations to the existing cottage
  • Plumbing, heating and electrics, bathroom and en-suite
  • Plasterboard, plastering, joinery and finishes (to come)
  • Full project management by our own team
Stage by stage

How this self build is coming together

From clearing the site in May 2026 to first fix in October. This build is still in progress, and we add each new stage as it happens.

  1. May 2026
    May 2026

    Before work started

    The original building is a traditional stone cottage in open countryside above West Kilbride. The plan was a two storey self build joined onto it, with two new bedrooms and a bathroom downstairs, and a master suite upstairs with its own dressing area, en-suite, snug and covered balcony.

  2. May 2026
    May 2026

    Site set up and clearing

    The site was set up and the ground cleared. Before the build could go any further, the access road was lowered so everything met the current building regulations.

  3. Late May 2026
    Late May 2026

    Foundations

    The foundations were set out, dug and reinforced to the engineer's design, with extra care where the new building meets the old stone walls of the cottage.

  4. June 2026
    June 2026

    Up to floor level

    Blockwork went up to floor level. Work paused briefly while the updated structural drawings came through to finalise the steel, and the time was used to get ahead with the groundworks.

  5. June 2026
    June 2026

    Drainage

    New drainage went in, including a soakaway for the surface water from the new roof.

  6. July 2026
    July 2026

    Ready for the slab

    Damp proof membrane and floor insulation went down across the whole footprint, ready for the new ground floor slab.

  7. July 2026
    July 2026

    The timber kit goes up

    The timber frame kit went up on the new slab, and from the air you could see the layout of the bedrooms, bathroom and hallway for the first time.

  8. Summer 2026
    Summer 2026

    First floor

    The first floor joists went in, with the opening trimmed for the new staircase.

  9. Summer 2026
    Summer 2026

    Upstairs walls

    The first floor was decked and the upstairs walls framed out for the master bedroom, dressing area, en-suite and snug.

  10. Summer 2026
    Summer 2026

    The roof

    The roof was framed and decked, then the ceilings insulated, making the new building weathertight.

  11. September 2026
    September 2026

    Windows in and first fix

    The windows and doors went in, the electricians started first fix, and the main opening was made through into the original cottage to join the old and new together.

  12. September 2026
    September 2026

    The team on site

    Our own team has run the job from day one, keeping the cottage protected and weathertight while the new building was joined on.

  13. September 2026
    September 2026

    The view from above

    By late September the roof was finished with its solar panels, and from the air the full scale of the new building next to the original cottage was clear to see.

  14. October 2026
    October 2026

    Outside nearly done

    With most of the outside complete, the scaffold came down and the house could be seen properly for the first time. The new doors were fitted and the solar panels went on.

  15. October 2026
    October 2026 · Latest

    First fix nearly done

    The plasterboard is on, the windows and doors are in, the bathrooms are framed and sheeted, and the balcony is formed and covered. Next comes plastering, second fix and the finishes.

On camera

Watch the build

Short updates filmed on site as the job has gone along.

Gallery

Project photos

Start your project

Planning something similar?

Tell us what you have in mind and where you are. We will come back to you to arrange a site visit.

CallTextWhatsApp